Contact: Doug Royer, Deputy Engineer (732-8885)
Purpose/Need: Resurfacing our existing county roads to improve the safety of the motoring public.
Action Necessary: Advertisement of Legal notice to obtain bids for the resurfacing of roads. Advertising for a total of 2 weeks with the legal notice advertised on June 16th and also placed on the County website. Bid opening to be on June 30th, 2011.
History of Project: This project is our annual resurfacing program. There are several roads within the Village of Williamsburg, these roads will be resurfaced as a part of our program.
Costs: The estimated construction cost is $1,890,000. This project will be funded with MVG funds. The two roads within the Village of Williamsburg will be reimbursed to the County upon payment to the contractor (estimated cost of $150,000).
Expected Outcomes: Resurfacing and repair of approximately 26 miles of Roadway.
Time Period: The completion date for this project is set at October 30, 2011.
Responsible Department(s): County Engineers Office.