2018 Road Resurfacing Program

2018 Road Resurfacing Program
Contact:   Doug Royer, Deputy Engineer (732-8885)

Purpose/Need: Resurfacing our existing county to improve the safety of the motoring public.

Action Necessary: Advertisement of Legal notice to obtain bids for the resurfacing of roads.  Advertising for a total of 2 weeks with the legal notice advertised on Thursday, May 17, 2018 and also placed on the County website.  Bid opening to be on Thursday, May 31, 2018.

History of Project: This project is our annual resurfacing program. The”plans”, as defined in section 200.1 of the General Provisions, are included in section VI of the Bid Documents.

Costs: The estimated construction cost is $667,280.85.  This project will be funded with MVG funds.

Expected Outcomes: Resurfacing 2.6 miles and repairing 23 miles of Roadway.

Time Period: The completion date for this project is set at August 31, 2018.

Responsible Department(s): County Engineers Office.

Project Documents:

Bidders List – PDF
Bid Results – PDF
Legal Notice – PDF

Project Status:

Completed