2011 Road Resurfacing

CONTACT:

Doug Royer, Deputy Engineer

513-732-8885

PURPOSE/NEED:

Resurfacing our existing county roads to improve the safety of the motoring public.

ACTION NECESSARY:

Advertisement of Legal notice to obtain bids for the resurfacing of roads.  Advertising for a total of 2 weeks with the legal notice advertised on June 16th and also placed on the County website.  Bid opening to be on June 30th, 2011.

HISTORY OF PROJECT:

This project is our annual resurfacing program.  There are several roads within the Village of Williamsburg, these roads will be resurfaced as a part of our program.

COSTS:

The estimated construction cost is $1,890,000.  This project will be funded with MVG funds. The two roads within the Village of Williamsburg will be reimbursed to the County upon payment to the contractor (estimated cost of $150,000).

EXPECTED OUTCOMES:

Resurfacing and repair of approximately 26 miles of Roadway.

TIME PERIOD:

The completion date for this project is set at October 30, 2011.

RESPONSIBLE DEPARTMENT(S):

County Engineers Office.

PROJECT DOCUMENTS:

2011 Road Resurfacing List – PDF

Legal Notice to Contractors – PDF

Bidders List 6-23-11 - PDF

Bid Results – PDF