CONTACT:
Doug Royer, Deputy Engineer
513-732-8885
|
PURPOSE/NEED:
Resurfacing our existing county to improve the safety of the motoring public.
|
ACTION NECESSARY:
Advertisement of Legal notice to obtain bids for the resurfacing of roads. Advertising for a total of 2 weeks with the legal notice advertised on Thursday, May 17, 2018 and also placed on the County website. Bid opening to be on Thursday, May 31, 2018.
|
HISTORY OF PROJECT:
This project is our annual resurfacing program. The”plans”, as defined in section 200.1 of the General Provisions, are included in section VI of the Bid Documents.
|
COSTS:
The estimated construction cost is $667,280.85. This project will be funded with MVG funds.
|
EXPECTED OUTCOMES:
Resurfacing 2.6 miles and repairing 23 miles of Roadway.
|
TIME PERIOD:
The completion date for this project is set at August 31, 2018.
|
RESPONSIBLE DEPARTMENT(S):
County Engineers Office.
|
PROJECT DOCUMENTS:
Bidders List – PDF Bid Results – PDF Legal Notice – PDF
|