CONTACT:
Doug Royer, Deputy Engineer
513-732-8885
|
PURPOSE/NEED:
Resurfacing our existing County Roads to improve the safety of the motoring public.
|
ACTION NECESSARY:
Advertisement of Legal notice to obtain bids for the resurfacing of roads. Advertising for a total of 2 weeks with the legal notice advertised on Thursday, May 9, 2019, and also placed on the County website. Bid opening to be on Thursday, May 23, 2019.
|
HISTORY OF PROJECT:
This project is our annual resurfacing program. The”plans”, as defined in section 200.1 of the General Provisions, are included in section VI of the Bid Documents.
|
COSTS:
The estimated construction cost is $2,083,067.00. This project will be funded with MVG funds.
|
EXPECTED OUTCOMES:
Resurfacing 19 miles and repairing 17 miles of Roadway.
|
TIME PERIOD:
The completion date for this project is set at November 16, 2019.
|
RESPONSIBLE DEPARTMENT(S):
County Engineers Office.
|
ROAD MAP/LIST:
2019 Road Resurfacing List
|
PROJECT DOCUMENTS:
Bidders List – PDF Bid Results – PDF Legal Notice – PDF
|