2020 Landslide Repairs, Phase II

CONTACT:

Amanda J. Beiting, Senior Engineer

513-732-8874

PURPOSE/NEED:

This project will repair existing landslides on the following roads:

Fruit Ridge Road

Bartlow Road

Felicity Cedron Rural Road

ACTION NECESSARY:

Advertisement of Legal notice to obtain bids for this landslide repair project.  This legal notice shall be advertised for two consecutive weeks.

HISTORY OF PROJECT:

All 4 landslides are similar with the following description: The landslide currently has an embankment failure causing a width restriction for the traveling public.  An application was filed with OPWC in August of 2019.  The OPWC application and agreement authorization was approved by Board on 4/8/2020 and the County Engineer executed the Grant Agreement on July 2, 2020.  The OPWC 2020 Landslides Project was approved for a grant maximum of $914,781.00, Phase 1 of the OPWC Project will utilize $505,601.99 of the approved grant, based on the bids. Phase 2 is estimated to utilize another $237,952.85.  The Felicity Cedron Landslide is not part of the OPWC agreement and will be paid 100% by MVG funds.

COSTS:

The construction cost is estimated as follows:

ProjectRoad/TownshipTotal Project Amount
2020 Landslides
Phase 2
Fruit Ridge Road #1/Washington Township
Fruit Ridge Road #2/Washington Township
Bartlow Road/Franklin Township
Felicity Cedron Rural Road/Franklin Township – [Not part of OPWC Agreement (100% MVG)]
OPWC Grant
MVG Funds
Project Cost
$353,987.15
$237,952.85
$591,940.00

EXPECTED OUTCOMES:

Stabilize the existing landslides and repair the roadways on Fruit Ridge Road, Bartlow Road, and Felicity Cedron Rural Road.

TIME PERIOD:

Project is to be completed by July 1, 2021.

RESPONSIBLE DEPARTMENT(S):

County Engineer’s Office.

PROJECT DOCUMENTS:

Bidders List – PDF

Bid Results – PDF

Legal Notice – PDF

PROJECT STATUS:

Completed