PURPOSE/NEED:
Replacing an existing deficient bridge.
|
ACTION NECESSARY:
Advertisement of Legal notice to obtain bids for the replacement of a bridge on Cedarville Road. Advertising for a total of 2 weeks with the legal notice advertised on November 10th and also placed on the County website. Bid opening to be on December 1, 2022.
|
HISTORY OF PROJECT:
The existing bridge is 28-foot span bridge load rated at 25 tons and bridge appraisal of 3. The proposed bridge will be a prestressed beam on capped pile abutments. OPWC funding was secured for this bridge in July 2021 and the project is now ready to proceed to public bidding
|
COSTS:
The estimated construction cost is $563,000.00. This project will be funded 79% from OPWC funds and the remaining 21% from local MVG funds
|
EXPECTED OUTCOMES:
Replacement of an existing 25-ton bridge on Cedarville Road.
|
TIME PERIOD:
The completion date for this project is set at September 1, 2023
|
RESPONSIBLE DEPARTMENT(S):
County Engineers Office.
|
PROJECT DOCUMENTS:
Bid Results – PDF Legal Notice – PDF
|