CONTACT:
Lyle Bloom, Chief Deputy Engineer
513-732-8880
|
PURPOSE/NEED:
This project will replace the Marathon Edenton
Road Bridge (C82-5.68), located in Wayne Township.
|
ACTION NECESSARY:
Advertisement
of Legal notice to obtain bids on Bid Express for this bridge project. The
legal notice will be advertised in the Clermont Sun on August 27, 2026, and will
be placed on the County website. Bid opening to be on September 17, 2026.
|
HISTORY OF PROJECT:
The bridge will be replaced using a 4-sided
concrete box with new wingwalls. An application was filed with OPWC in
September of 2024. The OPWC application and agreement authorization was
approved by the Board on 8/9/2024, and the County Engineer executed the Grant
Agreement on July 1, 2025.
|
COSTS:
Engineer’s
Estimate $398,105.00
The
project will be paid for using a combination of OPWC (69%) and MVG (31%) funds
|
EXPECTED OUTCOMES:
Replacement
of the existing bridge and removal of any load restrictions.
|
TIME PERIOD:
Project is to be completed by May 28, 2027.
|
RESPONSIBLE DEPARTMENT(S):
County Engineers Office.
|
PROJECT DOCUMENTS:
Legal Notice - PDF Bid Results - PDF
|