2020 Landslide Repairs, Phase II
Contact: Amanda J. Beiting, Senior Engineer (732-8874)
Purpose/Need: This project will repair existing landslides on the following roads:
Fruit Ridge Road
Bartlow Road
Felicity Cedron Rural Road
Action Necessary: Advertisement of Legal notice to obtain bids for this landslide repair project. This legal notice shall be advertised for two consecutive weeks.
History of Project: All 4 landslides are similar with the following description: The landslide currently has an embankment failure causing a width restriction for the traveling public. An application was filed with OPWC in August of 2019. The OPWC application and agreement authorization was approved by Board on 4/8/2020 and the County Engineer executed the Grant Agreement on July 2, 2020. The OPWC 2020 Landslides Project was approved for a grant maximum of $914,781.00, Phase 1 of the OPWC Project will utilize $505,601.99 of the approved grant, based on the bids. Phase 2 is estimated to utilize another $237,952.85. The Felicity Cedron Landslide is not part of the OPWC agreement and will be paid 100% by MVG funds.
Costs: The construction cost is estimated as follows:
Project |
Road/Township |
Total Project Amount |
2020 Landslides
|
Fruit Ridge Road #1/Washington Township Fruit Ridge Road #2/Washington Township Bartlow Road/Franklin Township Felicity Cedron Rural Road/Franklin Township – [Not part of OPWC Agreement (100% MVG)] |
OPWC Grant $ 353,987.15 MVG Funds $ 237,952.85 Project Cost $ 591,940.00 |
Expected Outcomes: Stabilize the existing landslides and repair the roadways on Fruit Ridge Road, Bartlow Road, and Felicity Cedron Rural Road.
Time Period: Project is to be completed by July 1, 2021.
Responsible Department(s): County Engineer’s Office.
Completed