Spring Grove Road Bridge No. C114-0.43 Rehabilitation (TA-15-24)
Contact: Lyle Bloom, Chief Deputy Engineer (732-8880)
Purpose/Need: This project will replace the beams on the Spring Grove Road Bridge (C114-0.43) and repair any other damage on the bridge, located in Tate Township
Action Necessary: Advertisement
of Legal notice to obtain bids on Bid Express for this bridge project. The
legal notice will be advertised in Clermont Sun on April 16, 2026, and will be
placed on the County website. Bid opening to be on April 30, 2026.
History of Project: The bridges currently
require a deck replacement due to deterioration and structural concerns. The
existing beams have experienced cracking, exposed reinforcing steel, and broken
prestressed steel cables, resulting in reduced structural integrity and concerns
for the traveling public. An application was filed with OPWC in September of 2024.
The OPWC application and agreement authorization was approved by the Board on 8/9/2024,
and the County Engineer executed the Grant Agreement on July 1, 2025.
Costs: The
construction cost is estimated as follows:
|
Project
|
Road/Township
|
Total
Project Amount
|
|
Spring
Grove Road Bridge Rehabilitation (C114-0.43)
|
Spring
Grove Road(C114)/Tate Township
|
Engineers Est. $548,490.00
|
Expected Outcomes: Rehabilitate
the existing bridge and repair the roadway on Spring Grove Road (C114).
Time Period: Project
is to be completed by November 20,2026.
Responsible Department(s): County Engineers Office.
Project Documents:
Bid Results – PDF
Project Status:
Pre-Construction